01 NOV 2013
Soil Filling Works
02 SEP 2013
Earthworks at Border Area & Tract for Roads and Future MS Tank 3500M3 Area
02 SEP 2013
Construction of Box Culvert (Outside Door 1&2)
02 SEP 2013
Construction of Convention Water Intake
02 SEP 2013
Construction of Concrete Beam for Drainage Stiffeners at Phase III Area
02 SEP 2013
Construction of Steel Structure Works for Genset & Pump House, Water Filling & Unloading, Sparepart Warehouse and Others
02 SEP 2013
Construction of Access Road
30 JUL 2013
Cut & Fill Works at Construction of Bridge and Air Manula Access Road Project
13 MEI 2013
Construction of Fencing
06 MEI 2013
Dismantled Tub Works of Unloading Station for Kernell
06 MAR 2013
Construction of Drainage
05 MEI 2013
Rehabilitation Works of Flood Controlling
20 MAR 2013
Procurement and installation of Paving at Parking Area (Phase III)