19 FEB 2016
Construction of Drainage at Fatty Acid Area
01 FEB 2016
Construction of Paving Block and breeze way for unloading Side B Area SBEP
04 JAN 2016
Construction of concrete road (exc. Helipad access) at Platina IV road
17 DES 2015
Dredging Works (Phase I)
16 NOV 2015
Construction of Effluent Pond
21 SEP 2015
Construction of Borepile ø 40 cm for Rail Weight Bridge
11 SEP 2015
Construction of Drainage for Mess Area and SBEP at Side B Area
10 SEP 2015
Land Clearing, Disposal and Soil Filling Works at CBS Plan Project
10 AGT 2015
Construction of Slope Protection for Fencing at Side B Area
30 JUL 2015
Additional Cladding Works for Generator Room
14 JUL 2015
Earthworks for Effluent Pond, Reservoir and Housing.
08 JUN 2015
Construction of Road Repairment
08 JUN 2015
Construction of Asphalt Concrete Access Road Section 1
25 MEI 2015
Construction of Revetment at SWRO area and Construction of Cansteen at Clarifier Tank Area